No building work can start without a building permit (permis de construire). A well-prepared application goes through quickly; a poorly prepared one can hold up a project for weeks. Here is how it works, step by step.
The framework
The building permit is provided for by Law No. 12-90 on urban planning. It is issued by the president of the municipal council and checks that your project complies with the zoning plan (plan d'aménagement) and the planning rules for the plot.
The application is made by the owner of the land, or by a person holding the owner's power of attorney.
Step 1 — Check what can be built
Before any drawing, ask the Urban Agency (Agence urbaine) for the planning information note (note de renseignements urbanistiques). It states what the zoning plan allows on your plot: use, height, footprint, setbacks. It is the foundation of the project.
Step 2 — Have the project designed by an architect
The application is handled by an architect registered with the Order of Architects. The architect prepares the plans (location, site layout, floor plans, elevations, sections) in line with the planning information note. Depending on the project, technical studies complete the file (reinforced concrete and, for earth construction, the RPCTerre 2011 seismic regulations).
Step 3 — File online on Rokhas
Applications are filed on the national platform Rokhas.ma, which is mandatory for planning authorisations. The file includes, among other things, the application form, the certificate of ownership of the land and the plans signed by the architect. Rokhas lets you track the review online.
Step 4 — The review
The file is examined by the relevant departments (municipality, Urban Agency and other bodies depending on the project). If a document is missing or a plan does not comply, the review is suspended until it is corrected: this is the leading cause of delay.
Law 12-90 provides that if the president of the municipal council does not respond, the permit is deemed granted two months after the application is filed. In practice, with Rokhas, many complete files are processed faster.
Step 5 — Permit granted: mind the deadline
A granted permit does not last forever: it lapses if foundation works have not started within one year of its issue. Plan the start of works before applying.
Step 6 — End of works: the occupancy permit
At the end of the works, the building's compliance is checked in order to obtain the occupancy permit (permis d'habiter). Without it, the house is not legally compliant.
The 4 mistakes that delay a permit
- Designing without having read the planning information note.
- Filing an incomplete application.
- Changing the project while it is under review.
- Letting the one-year deadline to start works run out.