Design & build

Turnkey construction in Marrakech

By the Minabayt team · Updated on

Turnkey construction in Marrakech means entrusting a single company with the design, the permits and the construction of your villa or apartment building, right up to the handover of the keys. With Minabayt, allow 10 to 13 months from the permit application to the handover, with a detailed, item-by-item quote.

At a glance

  • Projects: custom villas, apartment buildings, residences
  • Timeline: 10 to 13 months, from the permit application to the handover of the keys
  • Price: on a detailed, item-by-item quote
  • With or without land: we help you find the plot
  • Clients abroad: remote follow-up, photos and videos every week
  • Contact: WhatsApp +212 6 39 72 95 88

What our turnkey service includes

Our service covers the design, the permit and the whole build; a few items remain your responsibility.

Included

  • Design with an architect
  • Reinforced concrete plans
  • Permit filing and follow-up on Rokhas.ma
  • Structural work
  • Waterproofing and insulation
  • Plumbing and electrics
  • Joinery, doors and windows
  • Floor and wall finishes, painting
  • Bathroom fittings
  • Site supervision
  • Occupancy permit file

Not included

  • Land
  • Notary fees and registration duties
  • Swimming pool (on quote)
  • Outdoor works and landscaping (on quote)
  • Furniture and appliances

The 5 stages of your project

  1. Land and brief study (planning certificate, land title, budget)
  2. Design and plans (architect, reinforced concrete engineering firm)
  3. Building permit (filed on Rokhas.ma) — The building permit in Marrakech, step by step
  4. Construction (structural work, then fit-out and finishes, weekly photo updates)
  5. Acceptance and handover (occupancy permit)

How long does it take?

Allow 10 to 13 months from the permit application to the handover of the keys, for a villa as well as for a small building (for example R+3). The exact timeline depends on the land, the permit processing time and the finishes you choose.

Design and connection fees to plan for

On top of the construction work, plan for design fees and utility connection costs.

Design and connection fees, villa of 200 to 300 m²
ItemIndicative amount, villa of 200 to 300 m²
Architect (full assignment)7 to 12% of the construction cost
Reinforced concrete engineering firm12,000 to 20,000 DH
Surveyor and soil studyabout 5,000 DH
Water and electricity connections (RADEEMA)up to 20,000 DH depending on the distance to the network

Indicative amounts observed in Marrakech at the end of 2026; the exact amount appears in your quote. Municipal taxes and the social solidarity contribution are payable by the client and are not included in our prices.

Source: Minabayt team estimate, November 2026.

What does turnkey construction cost?

The price depends on the floor area, the land and the level of finish. We set it in a detailed, item-by-item quote, after studying your land and your brief. For a first estimate, send us the plot size and the number of rooms you want on WhatsApp.

Frequently asked questions

How long does turnkey construction take in Marrakech?

Allow 10 to 13 months from the permit application to the handover of the keys, for a villa or a small building.

Is the land included?

No. We can help you find a plot, then we design and build.

Can I follow the build from abroad?

Yes: a single point of contact, photos and videos every week and remote approvals.

Building in Morocco from abroad →

What costs should I plan for besides construction?

Architect (7 to 12%), engineering firm (12,000 to 20,000 DH), surveyor and soil study (about 5,000 DH), connections (up to 20,000 DH), plus the taxes payable by the client.

Villa or apartment building: what should I build on my land?

It depends on the zoning plan and on your goal.

Villa or apartment building: how to choose →

Conclusion

Our recommendation

In conclusion, ask for your land's planning certificate first, then for a detailed, item-by-item quote: it is the best protection against unpleasant surprises.